Mr. Chevrier: (Minister of Transport)
Liberal
1. Yes.
2. No formal agreement.
3. (a) $10,636,198; (b) $3,015,930; (c) $634,647.
4. (a) One-third of the cost or $5 million, whichever is the lesser; (b) balance of cost; (c) nil.
5. The estimate of the board of engineers is $68,000. Payable by the Canadian National Railways.
6. (a) July, 1950; (b) main piers in spring of 1951; (c) late 1953 or early 1954.
Subtopic: STRAIT OF CANSO BRIDGE